Offshore Wind Will Need Support Vessels – What Form Are You Going to Use?

Keith B. Letourneau and Douglas J. Shoemaker

As the United States develops offshore wind capacity, the need for vessels to support the industry for installation and maintenance will rapidly expand. While it may seem perfectly logical for the industry to adopt the BIMCO WINDTIME form, the SUPPLYTIME 2005 form is more common and generally known to the U.S. service and supply-vessel industry. In any case, we wholly expect that there will be a good deal of modifications to any form or perhaps use of bespoke agreements as the work comes online. We review here the various forms available and look at particular terms and issues we expect to be the subject of specific negotiation and modification.

SUPPLYTIME: Then and Now

The SUPPLYTIME form was first developed in 1975 to meet the rising demand for specialty vessels to support offshore oil and gas exploration and production. This form and its progeny became the leading time-charter terms for offshore-support vessels, and its use has spread beyond the oil and gas industry to include cable and pipe laying, seismic work, anchor handling, surveying, ROV and dive support, and other offshore and near-shore construction work. While there is a 2017 version of the SUPPLYTIME, it hasn’t been widely adopted in the United States, particularly since it came out after the substantial decrease in offshore oil and gas activity. (Interestingly, the drafting committee that developed the WINDTIME form differed from the SUPPLYTIME 2017 committee, and the difference is noticeable.) As for the U.S. offshore marine service and support industry, it appears that the SUPPLYTIME 2005 version remains prevalent at this time. (Obviously, any SUPPLYTIME form used with respect to the offshore wind industry would need to be logically amended to change oil and gas industry references to the appropriate wind-industry terms. For example, the term “offshore unit” in the SUPPLYTIME 2017 form is defined as “any vessel, offshore installation, structure and/or mobile unit used in offshore exploration, construction, pipe-laying or repair, exploitation or production.” There are also repeated reference to the defined term “well”.)

At the heart of the SUPPLYTIME form since the 1989 version came into play is a “knock-for-knock” indemnity provision, allocating liability regardless of fault with each party indemnifying the other for the injury or death of its personnel and for the loss of or damage to its property—without recourse. Initially, this was a difficult concept to accept in the United States—the idea that a party must indemnify another for a loss even though the loss was caused solely by the fault of the other party was a hard pill to swallow. However, in practice, the industry found it far more efficient for the parties to provide insurance for their own people and their own property and simply name the other party as an additional assured, rather than litigate every loss with each party claiming the other was at least partially to blame. The knock-for-knock indemnity concept is particularly efficient where a project involves a number of offshore contractors and all the parties agree to the same allocation of liability.

SUPPLYTIME vs. WINDTIME

The WINDTIME form, introduced in 2013, was primarily intended for offshore wind farm personnel transfer and support vessel services and was largely adopted from the SUPPPLYTIME 2005. Key differences from the SUPPLYTIME 2005 include:

  • the WINDTIME form expressly encompasses an indemnitee’s gross negligence, as well as simple negligence in the knock-for-knock indemnity obligations, but excludes intentional or willful misconduct, while the SUPPLTIME 2005 form only expressly addresses the indemnitee’s negligence;
  • the SUPPLYTIME 2005 form is more owner-friendly concerning cancellation with no provision for the recovery of damages; and
  • the WINDTIME form includes a broader waiver of consequential damages encompassing subcontractors.

It has been reported that the committee drafting the WINDTIME form initially considered, but quickly abandoned, the idea of including contract terms appropriate for installation vessels. We understand that industry practices for installation vessels were considered too varied and complex to reach consensus. Thus, the better option for installation vessels may be a SUPPLYTIME 2005 particularly modified to allocate liabilities and responsibilities, or a bespoke contract. Continue Reading